January, 2004
Letter of intent with the City of Pittsburg
February, 2004
Project introduced to CAISO San Francisco Stakeholder Group
August, 2004
Development Agreement executed with City of Pittsburg
Notice of Preparation issued under CEQA, with the City of Pittsburg as the lead Agency
July, 2005
FERC approval of TBC rate principles
September, 2005
CAISO Board of Governor's approval of need for TBC project as a reliability project
May, 2006
DEIR issuance
November, 2006
City of Pittsburg certification of Final EIR
August, 2007
Discretionary Acts complete - including approvals from the from the SF Board of Supervisors
August, 2007
Notice to Proceed to EPC Contractor
September, 2007
Financial Closing
November, 2007
Commencement of construction of Pittsburg converter station
January, 2008
Commencement of construction of San Francisco converter station
October, 2009
Cable laying begins
2010
Commercial operation